Tragedy in Dymer: death toll from drone strike rises to six British Minister Hamish Falconer harshly criticizes Putin and Trump's stance Geological study reveals a 405,000-year cycle of massive storms on Earth Shooting in Kharkiv: Police launch special operation following murder Goal-fest in Bergamo: Atalanta and Inter share the spoils Artem Dovbyk could change clubs: Ukrainian forward eyes move to Valencia Deteriorating weather conditions in Bila Tserkva: snow and ice expected US Congress Prepares Major Ukraine Aid Package to Counter Trump’s Policy Incident with Russian missiles in Poland: investigators confirm discovery of three targets Regional Energy Security: Consequences of Infrastructure Attacks Tragedy in Dymer: death toll from drone strike rises to six British Minister Hamish Falconer harshly criticizes Putin and Trump's stance Geological study reveals a 405,000-year cycle of massive storms on Earth Shooting in Kharkiv: Police launch special operation following murder Goal-fest in Bergamo: Atalanta and Inter share the spoils Artem Dovbyk could change clubs: Ukrainian forward eyes move to Valencia Deteriorating weather conditions in Bila Tserkva: snow and ice expected US Congress Prepares Major Ukraine Aid Package to Counter Trump’s Policy Incident with Russian missiles in Poland: investigators confirm discovery of three targets Regional Energy Security: Consequences of Infrastructure Attacks

Memorial Cemetery near Kyiv: Contractor Receives Additional UAH 879M Without Tender

🛡️ Security 2 min read 👁 0

An additional UAH 879 million has been allocated for the construction of the National Military Memorial Cemetery in the Kyiv region without open bidding.

🛡️Security

Key points

  • New UAH 879M contract signed without open tenders
  • Total cost of the first phase increased to UAH 3.02B
  • Works performed by the Building UA consortium in Markhalivka forest
  • Project includes utility network adjustments and landscaping changes

Large-scale construction works continue near the capital on the site of the future National Military Memorial Cemetery, which is being erected in the Markhalivka forest of the Fastiv district. The state institution acting as the customer of the project has signed a new additional agreement with the general contractor, the «Building UA» consortium. The value of the deal reached nearly 880 million hryvnias, and the documents were signed bypassing open tender procedures. Such decisions have sparked significant public resonance due to large budget expenditures under martial law.

Project Changes and Rising Costs

According to the updated project documentation, the total cost of the first phase of this memorial complex has increased to 3.02 billion hryvnias. The additional funds will be directed toward adjusting utility networks, relocating certain technical structures, expanding landscaping zones, and removing additional green spaces. Plans also include constructing a new columbarium wall and modifying the interior and exterior finishes of utility buildings. According to monitoring resources, by the time the agreement was signed, the contractor had already completed works worth nearly 857 million hryvnias.

The issue of transparency in such multi-billion infrastructure projects remains extremely sensitive for Ukrainian society. Citizens and civic activists closely monitor how state funds are spent to honor the memory of fallen defenders of Ukraine. Residents of Bila Tserkva and other cities in the region share the collective grief and expect maximum openness from authorities regarding every stage of creating national memorials.